The following are dates important to the progression of the 2021 Challenge.

  • 15.02: Release of first software phase

  • 18.02: First webinar with participating teams

  • 06.04-08.04: Checkins with teams

  • 08.04: Second webinar with participating teams

  • 22.04: Release of second software phase

  • 06.05-07.05: Checkins with teams

  • 01.08: Deadline for delivery of Technical Report

  • 08.08: Deadline for delivery of guidance system Docker container

  • 17.08-20.08: Competition dates, depending on travel restrictions

Webinars and voluntary check-ins with teams will be held roughly every 6 weeks, where all teams will be contacted beforehand.